⛈ SUBJECT TO CHANGE — Dates may shift due to weather. Check this page for the latest updates.
⚠ Road Resurfacing — Revised Target Start: Friday July 31, 2026
Language / Idioma:
📅 PAVING UPDATE — JULY 21: The correct manhole and valve risers have been ordered and are expected within about five business days. RDC is now targeting a paving start of Friday, July 31 (weather and parts permitting). The detailed day-by-day schedule below reflects the original plan and will be revised once the new sequence is confirmed. Board member Ryan Hazlett is coordinating communications over the coming weeks. Roads are safe to drive on and trash pickup continues normally.
West Rim Estates HOA — Westlake, Austin TX

Road Resurfacing 2026

Pavimentación de Calles 2026

Everything you need to know — schedule, parking plan, delivery guidance, and what to expect each day. Dates are being revised for a new target start of July 31.

Target: Week of July 31, 2026*
⛈ Important — Dates Subject to Change If there is significant rain in the days leading up to the start, or during the project itself, dates may shift. RDC will notify us immediately if the schedule changes and this page will be updated. Check back frequently in the days before the project begins.
Project Schedule
Schedule Being Revised The day-by-day schedule below reflects the original plan. Paving was postponed while RDC obtains the correct manhole and valve risers. RDC is now targeting a start of Friday, July 31. Exact daily assignments will be updated here once confirmed — please disregard the specific July 20–24 dates below until this notice is removed.
Monday
July 20
Milling + Proof Roll — Entire Community
RDC mobilizes at 6:00 AM. Mills the entire community following curb lines, taking right turns throughout. After milling, crew proof rolls all surfaces checking for soft spots. Residents may park on Trailview Mesa Drive overnight after proof roll — but must be out by 6:30 AM Tuesday. Noisy work begins around 6:30–7:00 AM.
Tuesday
July 21
ALL Cul-de-sacs Paved — Starting at Top (Teak Hawk Cv)
All cul-de-sacs paved Tuesday starting at Teak Hawk Cv and working down. Approximately 1 hour per cul-de-sac. RDC crew will knock on every door before paving your cul-de-sac — but do not rely on this. If your car is in a cul-de-sac being paved, plan to stay home 2–3 hours while the mat cools. Once cones are removed from your cul-de-sac, you may drive back in that evening. Trailview Mesa Drive is NOT paved Tuesday and remains open.
🚗 Parking TuesdayIf your cul-de-sac is being paved — move your car to Trailview Mesa Drive before 6:30 AM. You may park there overnight and return to your cul-de-sac once cones are removed that evening.
Wednesday
July 22
Remaining Cul-de-sacs + Trailview Mesa Drive Begins
RDC finishes any remaining cul-de-sacs then begins paving Trailview Mesa Drive — right side going up, left side coming back down, then center. Two lanes of traffic will always remain open on Trailview Mesa Drive throughout the day. Park Wednesday evening on the OPPOSITE side from active paving. Do not park in a cul-de-sac on the same side as active paving — you will not be able to cross over.
⚠ Parking Wednesday EveningPark on the side OPPOSITE to where paving is occurring. If paving the right side of Trailview Mesa Dr — park in a left side cul-de-sac, and vice versa.
Thursday
July 23
Finish Trailview Mesa Drive
RDC completes Trailview Mesa Drive. Once cones are removed everything is open — park normally and drive normally. If you have a driveway directly on Trailview Mesa Drive, watch for equipment and follow crew direction.
Friday
July 24
Buffer Day — Cleanup & Striping
Final cleanup, line striping, and any remaining touch-ups. Community fully open.
Following
Week
Gate Loop Repair + Punch List
Gate sensor loops replaced by subcontractor. Gate returns to normal operation. The gate will remain in the open position from the milling start through this repair.

* All dates are weather dependent and subject to change. Check this page and watch for email updates from PAMco.

Street-by-Street Paving Plan

Two-day paving approach — one side at a time

RDC will always keep one side of the community accessible. All cul-de-sacs are paved first, then Trailview Mesa Drive. Two lanes of traffic always remain open on Trailview Mesa Drive. Specific day assignments will be updated once the July 31 sequence is confirmed.

Day 1
First Paving Day
Right Side — Trailview Mesa Dr + Right Side Cul-de-sacs
~1,000 tons of asphalt — goal to complete entire right side in one day
Trailview Mesa Dr (right side) Trailview Mesa Terrace Meandering River Ct (right side) Pompano Cv Sparkling Brook Ln (right side) Teak Hawk Cv
Residents on the right side: move vehicles to the left side of the community before 6:00 AM on the first paving day. Left side remains open and accessible all day.
Day 2
Second Paving Day
Left Side — Trailview Mesa Dr + Left Side Cul-de-sacs
Remaining streets including cul-de-sacs off the left side
Trailview Mesa Dr (left side) Pescadero Cv Sparkling Brook Ln (left side) Calaw Cv Meandering River Ct (left side) Trailview Mesa Cove
Residents on the left side: move vehicles to the now-paved right side before 6:00 AM on the second paving day. Right side pavement will be solid enough to park on by this point.
What You Need to Know
1
Your Vehicle

RDC will begin mobilizing around 6:00 AM each day. Noisy work — milling and paving equipment — will begin around 6:30 to 7:00 AM. Plan accordingly if you need to leave early. During milling — park in your driveway, not on the street. Do not park on Trailview Mesa Drive at any time during the week — we must keep that road open for bidirectional traffic in and out of the community. Any vehicle parked on Trailview Mesa Drive will be subject to towing. During paving — move to the opposite side of the community per the plan above before 6:00 AM on the day your side is being paved. You are on your own for getting to and from your vehicle — there will be no community shuttle or golf cart service provided. Important: If you leave your car parked in your driveway on the day your side of the community is being paved, you will not be able to back out of your driveway for a minimum of 24 hours after paving is complete on your street. Fresh asphalt in front of your driveway must fully cure before any vehicle can drive over it. Plan ahead — if you need your car that day, move it to the other side of the community before paving begins. Fresh asphalt must remain clear of parked vehicles for a minimum of 24 hours. Driving over it is fine if no cones are present, but parking on it before it fully cures can leave marks and cause surface damage.

2
Contractors & Service Workers

Anyone scheduled to come to your home during the paving week — housekeepers, landscapers, pool service, construction crews — should reschedule that week or plan to park outside the community and walk in. We recommend canceling or postponing all non-essential service visits for the entire week. The less non-resident traffic the better.

3
Deliveries — Amazon, UPS, FedEx, DoorDash, Uber Eats

Non-resident delivery traffic should be kept at the gate during active paving. Consider meeting your delivery person at the entrance gate, or stocking up before the paving week to reduce delivery volume. Light passenger vehicles can drive over fresh asphalt — it is heavy vehicles like box trucks and appliance deliveries that are a real concern.

4
Heavy Commercial Vehicles

Moving trucks, appliance delivery trucks, box vans, and similar heavy vehicles should not drive on freshly paved roads for 5 business days after paving. If you have a major delivery or move scheduled, please reschedule it outside the paving week.

5
Trash Pickup

Do not cancel your trash service. RDC's crew will move trash cans as needed during milling. On the second paving day, trash pickup can proceed on the unpaved side of the street. RDC will coordinate around the trash truck.

6
The Gate

Milling will destroy the gate sensor loop. The gate will remain in the open position from the milling start through the loop repair the following week. This is expected and planned for. The community remains accessible throughout the project.

7
Driveway Tracking

Fresh asphalt may leave marks on driveways when vehicles drive over transitions. RDC is not responsible for cleaning up any prime coat or tack coat tracked onto driveways by personal vehicles during paving operations. Incidental tire marks from traffic are expected and normal and will need to be cleaned up at each resident's own expense.